Block 31 Update 5 – March 2018

Block 31 Construction Update 5 – March 2018

March 15th, 2018

Attention: CityPlace Residents’ Association and BIA

Re: Block 31 Construction – Update 5

Block 31 construction continues to progress quickly. The project is approximately 22% constructed
to date.

Substructure – Waterproofing and backfilling of foundation walls for both the north and south buildings are scheduled for the upcoming 2 weeks.

Superstructure – Pouring of structural slabs, foundation walls and columns as well as elevator and stairwell in the north and south buildings are scheduled for the upcoming 2 weeks.

Site access is expected to be maintained at the existing 2 east boundary locations; one at the south end of the east boundary and the other at the mid-point of the east boundary.